Complete the Haryana Orbital Rail Corridor
Bharatiya Janata Party · Haryana Assembly Election 2024
Last updated 21 Jul 2026
What does this status mean?
Implementation is progressing towards the commitment.
Status describes delivery. Confidence describes how strong the available evidence is.
Original manifesto wording
“हम भारत सरकार के सहयोग से केएमपी के ऑर्बिटल रेल कॉरिडोर का निर्माण पूरा करेंगे।”
Our Assessment
The promise is to complete the Haryana Orbital Rail Corridor with central support. HRIDC records land awards across the full route, active civil and electrification works, financial closure for Part A and ₹3,100.69 crore of cumulative project expenditure by August 31, 2025. An 8.7 km Patli-Manesar-MSIL connectivity section was commissioned for freight traffic on June 17, 2025. The remaining corridor is not complete, but the official programme contains staged commissioning targets extending to April 2029 and shows substantial physical and financial progress. This supports on_track rather than fulfilled or merely partial. The Hindi original is preserved in original_text and the English title is a neutral translation. Budget: the revised project cost is ₹11,709 crore, ₹600 crore was approved for 2025-26 under special capital assistance and cumulative expenditure reached ₹3,100.69 crore.
Sources & Evidence
Promise Timeline
HRIDC published project status and staged commissioning targets through April 2029.
View sourceHRIDC recorded ₹3,100.69 crore cumulative expenditure and active work on awarded packages.
View sourceThe 8.7 km Patli-Manesar-MSIL connectivity section was commissioned for freight traffic.
View sourceRelated Promises