Partially Donehigh confidenceTechnology

Provide universal broadband and Wi-Fi across rural Gujarat

Bharatiya Janata Party · Gujarat Legislative Assembly Election 2022

Last updated 15 Oct 2026

What does this status mean?

Meaningful delivery has occurred, but the stated commitment is incomplete.

Status describes delivery. Confidence describes how strong the available evidence is.

Original manifesto wording

“Aim to make Gujarat the first state in the country to achieve universal Broadband and Wi-Fi connectivity across rural areas of Gujarat”

From the Bharatiya Janata Party manifestoView Manifestop.35

Our Assessment

Gujarat has implemented substantial rural broadband and public Wi-Fi services, but the evidence does not establish universal coverage. A March 2025 parliamentary reply recorded all 14,320 Gram Panchayats planned under BharatNet Phases I and II as service-ready and 1,23,277 fibre-to-the-home connections using the network in Gram Panchayats and villages. The Governor's February 2026 address also reported operating Rural Wi-Fi services at more than 7,685 Gram Panchayat offices in 22 districts, including one free hour daily. These are service-delivery records, rather than plans alone. A June 2025 agreement launched the Amended BharatNet programme to upgrade connectivity and extend it across all Gram Panchayats and non-GP villages on demand. An April 2026 parliamentary table subsequently recorded 14,563 service-ready points against 14,621 Gram Panchayats and equivalents, with a warning that some Panchayats may have more than one point. These measures are different: a service-ready fibre point does not prove reliable broadband and functioning public Wi-Fi throughout every rural settlement. No evidence reviewed establishes universal rural coverage or the claimed first-state position. The numerical and geographic scope therefore remains only partly delivered, supporting Partially Done with high confidence.

The reasoning behind the verdict

Why this assessment?

Reviewed

01 · Delivery status

Why partially done?

Operational rural Wi-Fi and FTTH services demonstrate meaningful delivery. Universal broadband and Wi-Fi coverage of rural areas, including non-GP villages and last-mile access, has not been established. Service-ready point counts cannot be treated as completed village coverage.

Service-ready fibre points, Gram Panchayats, villages and functioning public Wi-Fi coverage have different denominators. No universal-coverage percentage is inferred.

02 · Strength of evidence

Why high confidence?

Parliamentary replies, the Governor's address and Gujarat's fibre-network department give direct evidence of actual services and the limits of the published coverage measures. Multiple primary sources support partial implementation, while none certifies universal broadband and Wi-Fi availability.

What would help us reassess?

The documents that could clarify delivery of this commitment.

  • A settlement-level list of rural villages with operational broadband and public Wi-Fi, including non-GP villages
  • Current uptime, speed and active-user data for rural public Wi-Fi access points
  • Independent confirmation that all rural households and institutions can obtain reliable last-mile broadband
  • Comparable state-level evidence supporting the claimed first-state achievement

Status describes delivery. Confidence describes the evidence.

Read our methodology ↗

Promise Timeline

1 Apr 2026

A parliamentary answer listed Gujarat's 14,563 BharatNet service-ready points against 14,621 Gram Panchayats and equivalents. The table explicitly notes that some Panchayats may have multiple points, so this cannot be converted into a unique-Panchayat or village completion percentage.

View source
16 Feb 2026

The Governor's address reported that villagers were using Rural Wi-Fi services at more than 7,685 Gram Panchayat offices in 22 districts, with the first hour free each day. The programme was undertaken during 2022-23.

View source
24 Jun 2025

The Centre, Gujarat, BSNL and GFGNL signed an Amended BharatNet agreement to upgrade the network and extend it across Gram Panchayats and non-GP villages on demand. The agreement describes further rollout, rather than certifying universal coverage.

View source
26 Mar 2025

A parliamentary reply reported 14,320 planned Gujarat Gram Panchayats service-ready under BharatNet Phases I and II, 55,418 km of optical fibre and 1,23,277 FTTH connections in Gram Panchayats and villages. These figures describe network and subscriber delivery, rather than universal Wi-Fi coverage.

View source
ShareWhatsAppPost on X