Partially Donehigh confidenceEnergy

Double wind electricity generation using onshore and offshore parks

Bharatiya Janata Party · Gujarat Legislative Assembly Election 2022

Last updated 15 Oct 2026

What does this status mean?

Meaningful delivery has occurred, but the stated commitment is incomplete.

Status describes delivery. Confidence describes how strong the available evidence is.

Original manifesto wording

“Double power generation through wind energy using offshore and onshore wind parks.”

From the Bharatiya Janata Party manifestoView Manifestop.31

Our Assessment

Gujarat's annual wind output has risen to about 33,706 million units in FY2025–26. Against FY2021–22, the last complete pre-election year, doubling would require about 35,710 million units. Output is therefore close to, but below, that benchmark. Offshore development remains in preparation; approvals are not counted as operating generation.

The reasoning behind the verdict

Why this assessment?

Reviewed

01 · Delivery status

Why partially done?

Recorded electricity output remains below the doubling benchmark, and offshore generation has not been verified.

FY2025–26 output versus twice FY2021–22's 17,854.77 MU. This disclosed pre-election baseline is an assessment choice; the manifesto did not specify one. Includes statewide output, with offshore delivery assessed separately.

02 · Strength of evidence

Why high confidence?

Parliamentary replies publish annual generation directly; the baseline is explicitly stated rather than inferred from installed MW.

What would help us reassess?

The documents that could clarify delivery of this commitment.

  • A full-year wind-generation total reaching twice the selected pre-election baseline
  • Official clarification of the intended baseline year
  • Commissioning and actual electricity output from Gujarat offshore wind projects

Status describes delivery. Confidence describes the evidence.

Read our methodology ↗
Annual wind electricity generated94%
33,706million units/yearcurrent35,709.54million units/yeartarget

Promise Timeline

22 Jul 2026

Parliamentary reply recorded Gujarat wind output of 33,706 million units in FY2025–26.

View source
14 Jun 2026

Government described offshore wind as under development, including a proposed 500 MW Gujarat component.

View source
31 Mar 2022

Pre-election reference: Gujarat generated 17,854.77 million units of wind electricity in FY2021–22.

View source
ShareWhatsAppPost on X
ManifestoWatch mascot — contribute character

Have evidence on this promise?

Help us track this promise by submitting news articles, government orders, or any other evidence you've found.

Submit Evidence
Double wind electricity generation… — Status | ManifestoWatch