Complete Tehri Pumped Storage Project
Bharatiya Janata Party · Uttarakhand Legislative Assembly Election 2022
Last updated 4 Jul 2026
What does this status mean?
Meaningful delivery has occurred, but the stated commitment is incomplete.
Status describes delivery. Confidence describes how strong the available evidence is.
Original manifesto wording
“Tehri Pumped Storage — 1000 MW — ₹ 4,825.6 crores.”
Our Assessment
Tehri PSP has entered commercial operation for Units 1, 2 and 3, while commissioning of Unit 4 was still under progress in THDC commercial disclosures. Most of the 1,000 MW project has progressed to commercial operation, but full completion was not verified. Budget: Later cost reporting around ₹8,339 crore; manifesto listed ₹4,825.6 crore.