Fulfilledhigh confidenceEnergy

Complete Naitwar Mori Hydro Electric Project

Bharatiya Janata Party · Uttarakhand Legislative Assembly Election 2022

Last updated 4 Jul 2026

Naitwar Mori Hydro Electric Project — 265.5 million units of electricity every year — ₹ 947.89 crores.

From the Bharatiya Janata Party manifestoView Manifestop.42

Our Assessment

high
high

SJVN commissioned both units of the 60 MW Naitwar Mori Hydro Power Station in December 2023 and commercial generation began. The listed hydro project is operational, so the delivery objective is met. Budget: Manifesto listed ₹947.89 crore.

Promise Timeline

9 Feb 2022

BJP manifesto promised: Naitwar Mori Hydro Electric Project — 265.5 million units of electricity every year — ₹ 947.89 crores.

View source