On Trackhigh confidenceAgriculture

Complete the Eastern Rajasthan Canal Project in a time-bound manner

Bharatiya Janata Party · Rajasthan Legislative Assembly Election 2023

Last updated 26 Jul 2026

हम केंद्र सरकार के साथ मिलकर पूर्वी राजस्थान नहर परियोजना (ईआरसीपी) को समयबद्ध तरीके से पूरा करेंगे।

From the Bharatiya Janata Party manifestoView Manifesto

Our Assessment

high
high

The manifesto promised time-bound completion of the Eastern Rajasthan Canal Project with the Union government. Delivery is proceeding through the Revised Parvati-Kalisindh-Chambal Link Project, later described as the Modified PKC-ERCP or Ram Jal Setu Link Project; this is a substantive match because it retains the same drinking-water and irrigation objectives and beneficiary region. Rajasthan reported a Centre-state MoU, first-phase approvals and work orders of about Rs 9,600 crore, and commencement of works in the 2025-26 Budget. The project is not complete, but major funded implementation is active and consistent with a credible path during the term. Budget: Official documents record a proposed project cost of Rs 45,000 crore and first-phase approvals and work orders of about Rs 9,600 crore.

First-phase approvals and work orders verified21%
9,600Rs crore project costcurrent45,000Rs crore project costtarget

Promise Timeline

19 Feb 2025

Budget 2025-26 reported commencement of works under the Modified PKC-ERCP.

View source
10 Jul 2024

The Modified Budget reported first-phase ERCP approvals and work orders of about Rs 9,600 crore.

View source
8 Feb 2024

Rajasthan reported a Centre-state MoU for ERCP and a proposed project cost of about Rs 45,000 crore.

View source
ShareWhatsAppPost on X
ManifestoWatch mascot — contribute character

Have evidence on this promise?

Help us track this promise by submitting news articles, government orders, or any other evidence you've found.

Submit Evidence